Create a work order from a date proposal

  • Updated

Recurring activities from time schedules and object monitoring lines appear as date proposals in the work planning Role Center as soon as they are due. You can create work orders from one or more date proposals in just a few steps. The details from the time schedule are transferred.

Prerequisites

  • The work planning Role Center is set up for your user with a date proposal name, see Set up date proposals for work planning. If this setup is missing, maintool displays Setup for the Role Workplanning for the user … not available.
  • A number series for work orders is specified in the Work Order Nos. field in the Work Order Management Setup (Numbering FastTab).

Open the date proposals

  • In the work planning Role Center, choose the Overdue Date Proposals tile (Overdue section) or the Future Date Proposals tile (In Future/Planning section).
  • Alternatively, use the Date Proposal Worksheets menu in the Role Center to open all date proposals of your date proposal name.

In both cases, the Date Proposal List opens. Choose Update to have maintool recalculate the date proposals.

If you want to see date proposals for a specific period or with your own filters, search for the Date Proposal Worksheet page. There, you create work orders in the same way using Function › Create Work Order › For Current Record or For Marked Records. The filter options are described in Visualization of date proposals.

Create a work order

From one date proposal

  1. In the Date Proposal List, select the date proposal.
  2. Choose Create Work Order › Create Work Order For Current Record.
  3. If several number series are set up for work orders, maintool asks whether you want to create a work order. Select the number series and confirm. If there is only one number series, this question is skipped.
  4. maintool reports that the work order was created and asks Show Document?. Choose Yes to open the work order right away.

From several date proposals

  1. In the Date Proposal List, select several date proposals.
  2. Choose Create Work Order › Create Work Order For Marked Records.
  3. Choose how the date proposals are combined:
    • One Work Order: All selected date proposals go into one common work order (collective work order).
    • Multiple Work Orders: A separate work order is created for each date proposal (individual work orders).
  4. Select the number series if required and confirm.
  5. For one work order, maintool asks Show Document?, for several Show Document List?. Choose Yes to open the work order or the list of new work orders.

You can only process date proposals with the same Reference Object together, for example only mounting positions or only technical components. Otherwise, maintool stops with the message You can only process date proposal lines with the same Reference Object!. maintool does not check further details such as work order category, type of activity or cost center. For clean evaluations, only combine date proposals with the same details in a collective work order.

Result

The work order has the status Planning and is linked to the time schedule. The date proposal disappears from the date proposal list. You can find the work order in the Role Center, for example under Curr. Work Orders - Planning, or in the list of work orders.

  • Type of Origin shows Time Schedule or Object Monitoring Line.
  • The following details, among others, are transferred from the time schedule: descriptions, person in charge, responsible department, shift, priority, type of activity, work order category, work plan, work order duration, standstill, budget and posting details (for example the work order posting group). In addition, the planning lines, comments and texts of the time schedule are transferred.
  • The Execution Date-Time is taken from Next Action at Date-Time of the date proposal, shifted by the execution day of the time schedule if applicable. If a work order duration is specified, maintool calculates the planned completion date-time from it.
  • For date proposals from object monitoring lines, the technical object is assigned with Reference Object and Detail No.
  • Dimensions: For an individual work order, maintool transfers the dimensions of the time schedule or, for object monitoring lines, the default dimensions of the technical object. For a collective work order, no dimensions are transferred; enter them yourself on the Accounting FastTab.
  • For a collective work order, the header data comes from the first date proposal. The other date proposals are added as further Origin Lines in the work order, and their planning lines and objects are added.

Next, you plan and schedule the work order, see Schedule a work order and set it to execution.

Add a date proposal to an existing work order

Instead of creating a new work order, you can also add a date proposal to an existing work order with the status Planning, for example if maintenance is carried out together with other work on the same object anyway.

  1. In the Date Proposal List, select one or more date proposals.
  2. Choose Expand Work Order › Expand Work Order For Current Record or Expand Work Order For Marked Records and confirm the question.
  3. Select the work order. Only work orders with the status Planning and the same reference object are offered.

The date proposal is added to the work order as an origin line, including its planning lines.

If you mix different kinds of work in one work order, for example maintenance and repair, work order category, type of activity and cost center are mixed as well. For follow-up work discovered during maintenance, a separate follow-up work order is usually the better choice, see Create a follow-up work order.

Why is a date proposal missing?

maintool only shows a date proposal if a new date is possible. An expected date proposal is missing, for example, if:

  • the time schedule or the object monitoring line has the status Blocked or Expired. maintool sets the status Expired automatically as soon as the Scheduling End Date-Time is reached; after that, no more dates are created.
  • the technical object is blocked.
  • the work order for the previous date has not yet reached the stage defined in the time schedule under Set next Action at, for example finishing. Only then does maintool calculate the next date. A canceled work order counts as completed, see Cancel a work order.
  • the date lies outside the period covered by your date proposal name and your Role Center setup, or a filter excludes it.
  • the date proposals have not been recalculated since the last change. Depending on the Calculation Interval of your Role Center setup, this only happens hourly or daily; choose Update in the Date Proposal List to start the calculation immediately.

You cannot create a work order from preview dates (Date Preview), only from the next due date. Date proposals that originate from an existing work order cannot be converted into a work order either.