The work order is the central document of Work Order Management. In it, you plan which work is required on which technical objects, who carries it out and which items are needed. Hours, items and external services are then posted via the work order. This article explains the kinds of work orders, where a work order originates from and what is created when you post.
Structure of a work order
The work order card is divided into the following FastTabs:
- General – description, responsibility, work order status, origin and indicators such as Standing Order and Blocked.
- Technical Object – the reference object and the affected technical objects (details).
- Lines – planned resources, resource groups, items, and external services.
- Activity, Accounting and Appointments – information about the activity, account assignment and scheduling.
For a description of all fields, see Fields of the work order card; for the FactBoxes, see FactBoxes of the work order card. The phases a work order goes through are described in Work order status.
Kinds of work orders
| Kind | Purpose | Indicator |
| Work order | The standard case: a specific job, for example troubleshooting or maintenance from a time schedule. | – |
| Standing order | Remains open for a longer period so that hours and items can be posted continuously, for example for general workshop activities. | Standing Order toggle on the General FastTab. Standing orders appear in the Role Center in the Standing Work Orders tile and not in the Curr. Work Orders - Planning and Curr. Work Orders - Execution tiles. |
| Follow-up work order | If further work results from a work order, you create a subordinate work order from it. It takes over the reference object and dimensions, among other things. | Type of Origin Work Order; up to 8 levels |
| Subsequently recorded work order | For work that has already been done, for example after urgent troubleshooting. The work is recorded, posted and documented afterwards. | Depending on the method, no Type of Origin or Type of Origin Work Order Feedback |
Origin of a work order
The Type of Origin field on the General FastTab shows what a work order was created from, and the Origin No. field shows the number of the source. The Origin Lines action opens the Work Order Origin Lines list with all sources of the work order.
| Type of Origin | Meaning |
| blank | The work order was created manually, including via a wizard or the Equipment Information Center. |
| Work Order Request | The work order was created from a work order request. |
| Time Schedule | The work order was created from a time schedule, usually via a date proposal. |
| Object Monitoring Line | The work order was created from an object monitoring line, usually via a date proposal. |
| Multiple | The work order has several origin lines, for example because several date proposals were combined in one work order. |
| Work Order | The work order is a follow-up work order. |
| Work Order Feedback | The work order was created when posting a work order feedback for which no work order existed yet. |
| Contract Position | The work order was created from a contract position in Contract Management. |
Origin lines can be reported finished individually, for example if a work order bundles several dates from time schedules. When you report the work order finished, maintool asks whether open origin lines should be reported finished as well. See Finish and close a work order.
What is created when you post
Like Business Central, maintool works according to the entry principle: every posting creates entries that can no longer be changed or deleted. You can post to a work order from the status Execution on, for example via work order feedback, the Work Order Journal, time recording or purchase and sales documents related to the work order. The following is created:
- Work order ledger entries – what was posted: resource, item or external service with quantity and date.
- Work order value entries – the related amounts (costs and, where applicable, sales amounts).
- The usual Business Central entries, for example item ledger entries for consumed items and resource ledger entries for resources.
The costs are transferred to the general ledger (G/L entries) automatically if Automatic Cost Posting is enabled in the Work Order Management Setup (General FastTab). Otherwise, you post them with the Post to G/L action on the work order card. See Posting setup – overview.
You can view the entries of a work order on the work order card and in the Work Orders list with the Ledger Entries and Value Entries actions. The Statistics action compares planned and actual values.
Blocked work orders
With the Blocked toggle on the General FastTab, you put a work order on hold temporarily. As long as it is blocked,
- its status cannot be changed to Execution, Finished, Closed or Canceled,
- nothing can be posted to the work order – neither work order feedback nor journal lines, time recordings or costs to the general ledger,
- no purchase or sales lines can be assigned to the work order,
- no bills of materials can be exploded in the work order.
To remove the block, turn off the Blocked toggle again.
Ways to create a work order
| Starting point | Article |
| A fault was reported as a work order request. | Create a work order from a work order request |
| A date from a time schedule or object monitoring is due. | Create a work order from a date proposal |
| You want to create a work order directly. | Create a work order manually |
| You are working in the Equipment Information Center and have already selected the technical object. | Create a work order from the Equipment Information Center |
| Further work results from an existing work order. | Create a follow-up work order |
| You need an order for ongoing postings. | Create a standing order |
| The work has already been done. | Record work that has already been completed |
After creating the work order, you assign the technical objects (Assign technical objects to a work order), enter the planning lines (Enter planning lines) and set the work order to execution (Schedule a work order and set it to execution).