Enter planning lines

  • Updated

On the Lines FastTab of the work order, you plan what is needed for the work: material, personnel and external services, as well as flat rates that you invoice to the customer. The planning lines result in the planned costs of the work order. maintool also uses them for availability and conflicts, for purchase documents and for reporting as planned.

Planning lines are not mandatory. You can execute and report a work order without planning lines in the same way; it then simply has no planned costs.

Prerequisites

  • The work order has the status Planning.
  • From the status Execution onwards, you can only change or add lines if Extended Work Order Planning applies to the work order. maintool takes this setting from the Work Order Management Setup (General FastTab) when the work order is created. From the status Finished onwards, no changes are possible.

Line types

You define the kind of line in the Type column:

Type Used for Selection in No.
(blank) Text line, for example a note Standard text, or free text in Description
Item Material and spare parts Inventory and non-inventory items that are not blocked and have no maintool Item Type
External Service Work by external companies Items of type Service, see Set up external service items
Resource A specific person or machine Resources that are not blocked
Resource Group Capacity of a group if the person is not yet known Resource groups
Sales Item Flat rates that are only invoiced and not consumed, for example a maintenance flat rate (see below) Non-inventory items with the Item Type Std.-Invoice Text that are not blocked, see Set up standard invoice text items

Enter a planning line

  1. Open the work order and go to the Lines FastTab.
  2. In a new line, select the Type and, in No., the item, resource or resource group.
    maintool fills in the description, unit of measure and prices. For items, the Location Code from the Work Order Management Setup (General FastTab) is suggested.
  3. Enter the Quantity, for resources, for example, the planned hours.
  4. For resources and resource groups, select a Work Type Code if required (see below).
  5. Check the Unit Cost and Line Amount.

Each line receives the Execution Date-Time of the work order. If you move the date in the work order, maintool moves the lines accordingly. You can show further columns such as Execution Date-Time, Reported Quantity or the dimensions using personalization.

Work types

The Work Type Code is only available for lines of type Resource and Resource Group. Use the work type to distinguish, for example, regular hours from overtime or on-call duty.

  • maintool takes the unit of measure of the work type and recalculates the prices.
  • Without a work type, the base unit of measure of the resource or the unit of measure of the resource group applies.
  • When reporting, maintool assigns posted hours to a planning line with the same work type. Therefore, plan and report work types consistently.

Sales items

Lines of type Sales Item are pure sales lines for flat rates that you invoice to the customer. maintool determines the Unit Price and Unit Cost as for item lines. The following applies to these lines:

  • With Create Sales Quote and with Create Sales Invoice (invoicing method Fixed Price or Mixed), maintool transfers them to sales documents, see Create a sales quote or sales invoice from a work order.
  • maintool does not transfer them to work order feedbacks, not even with Report as Planned.
  • They cannot be requested or ordered. If they are selected, Create Purchase Quote or Create Order stops with a message.
  • They do not count as item demand, cannot be reserved and do not cause conflicts.
  • This type is not available in time schedules and work plans.

Available from version 20261000.16: Work order lines of type Sales Item and the Invoicing Method field in Create Sales Invoice. Before that, Create Sales Invoice only invoices the posted consumption.

Explode BOM

With Explode BOM, you transfer several items to the planning lines at once. There are two variants.

Bill of materials of a technical component

Enter wear parts that are needed repeatedly in the bill of materials of the technical component. You can then transfer these parts to every work order for the component.

  1. Make sure that Technical Component is selected as the Reference Object and that the component is assigned, see Assign technical objects to a work order.
  2. Choose the Details action.
  3. Select the component and choose Explode BOM.

maintool appends all items of the Technical Component BOM to the planning lines as lines of type Item with the quantity specified there. Delete lines you do not need or change the quantities. The bill of materials of the component remains unchanged.

Item bill of materials

  1. Enter a line of type Item with a BOM item and the quantity.
  2. On the Lines FastTab, choose Functions > Explode BOM.
  3. Select where the dimensions should come from: Copy dimensions from BOM or Retrieve dimensions from components.

maintool replaces the BOM line with the components of the bill of materials, multiplied by the quantity.

Both variants only work as long as the lines can be changed, and not for blocked work orders. Otherwise, a message such as The Work Order … must be smaller than Execution! appears. If the stockout warning is active, maintool checks the availability of the items first. You cannot explode an item line that is already reserved.

Unscheduled lines

maintool treats lines that are added after the change to Execution as unscheduled lines. Unscheduled lines are created

  • when you add a line or change the No. of a line in the status Execution with Extended Work Order Planning,
  • when you use the Create unscheduled Work Order Line function in the work order journal, see Post hours and material in the work order journal.

Unscheduled lines do not count towards the planned costs of the work order (Planned Amount) or the planned value in the statistics. For purchase quotes, purchase orders and sales quotes, they are included like planned lines.

Available from version 20260800.0: Unscheduled lines are no longer skipped when you create a purchase quote or a sales quote from the work order.

Outstanding quantity

For each planning line, maintool keeps track of how much has already been reported:

  • Reported Quantity: quantity posted using a work order feedback or the work order journal.
  • Outstanding Quantity: Quantity minus Reported Quantity, never less than 0. If it is 0, the line is considered completely reported.

If you post a feedback without reference to a specific line, maintool distributes the quantity to matching planning lines (same No., for resources the same work type) that still have an outstanding quantity. Resource hours are also assigned to lines of the related resource group.

The outstanding quantity is the remaining demand. It counts for availability and conflicts, for item demand in planning and for the budget. You see it as a column on the Planned Work Order Lines page in the budget, see Assign a work order to a budget and calculate costs.

Further functions in the lines