The technical objects define what is being worked on in the work order. The assignment is more than information: maintool uses it to transfer dimensions such as the cost center and the location of work. In addition, you can then transfer the bill of materials of a technical component to the planning lines.
If you created the work order from a technical object, with the wizard or from the Equipment Information Center, the object is already assigned. You need these instructions if you created the work order without an object or want to add further objects.
Prerequisites
- The work order has the status Planning. From Execution onwards, the reference object and the work order details can no longer be changed.
Assign a technical object
- Open the work order.
- On the Technical Object FastTab, in the Reference Object field, select the kind of object: Component Address, Mounting Position, Technical Component or Vehicle.
- Choose the Details action.
The Work Order Details page opens. - In the No. column, select the object. Using Select from full list, you see all objects with filter options.
maintool transfers the description from the object, for vehicles also the licence number and the mileage. - If required, add further objects in new lines.
- Close the page.
On the work order card, the Detail No. field now shows the number of the object, or (Multiple) if there are several objects. Using the button in the field, you open the object card or the list of assigned objects. You can also edit and delete the objects in the Work Order Details FactBox.
What the assignment does
Dimensions (for example cost center)
For the first object, maintool transfers its default dimensions to the work order and to existing planning lines. If the object has no dimensions, maintool continues searching in the higher-level object:
- Component address: in the component address from the Component Address from field
- Mounting position: in the assigned component address that is marked as Cost Relevant
- Technical component: in the higher-level component (Component from), then in the mounting position
- Vehicle: in the mounting position from the Actual Location field
If the work order already has dimensions, for example from the work order category, maintool asks whether to delete them. With Yes, only the dimensions of the object apply. With No, both are combined; for the same dimension, the value of the object wins.
Several objects
A work order can contain several objects, but only of the same kind. The kind is defined by the Reference Object field.
As soon as you add a second object and the work order has dimensions, maintool asks: Work Order … did decreed about more than one Detail Line, there for you should delete Dimensions. Delete Dimensions?
- Yes: maintool deletes the dimensions in the work order and in the planning lines. Afterwards, enter the correct cost center yourself on the Accounting FastTab.
- No: The dimensions of the first object remain and apply to the entire work order.
If the objects belong to different cost centers and the costs are to be posted separately, it is better to create a separate work order for each cost center.
Location of work
If a Locality Code is specified for the object, maintool transfers it to the work order as the location of work (not for vehicles). For more information, see Enter the location of work.
Further effects
- For a technical component, you can explode the bill of materials on the Work Order Details page, see Enter planning lines.
- When changing to the status Execution, maintool checks whether at least one object is assigned for the reference object. If not, the status change is canceled, see Schedule a work order and set it to execution.
Change the reference object or remove an object
- If you change the Reference Object, maintool deletes all assigned objects after a confirmation. If the work order has origin lines, for example from a time schedule, maintool also deletes them after another confirmation. Origin lines from work order requests and work orders remain.
- If you delete an object from the Work Order Details, maintool does not adjust the dimensions. If required, check them using the Dimensions action.