For every planning line of a work order, maintool checks whether staff, material and external services are available on the planned execution date. If not, there is an availability conflict. You see conflicts in the planning lines and in the Work Order List; there the Work Order Conflicts FactBox shows the affected lines and offers solution proposals.
The four types of conflict
maintool only considers lines that still have an outstanding quantity (quantity minus reported quantity). Lines that are fully reported never have a conflict. The Execution Date of the line is decisive; if it has no date, the work date is used. The comparison is made per day in the base unit of measure.
| Type of conflict | Applies to lines of type | A conflict occurs if … |
| Resource conflict | Resource, only resources of the type Person | the outstanding quantities of all work order lines for this resource on the same day are greater than the capacity of the resource on that day. Allocations from projects or service orders are not counted here. |
| Resource group conflict | Resource Group | the outstanding quantities of all work order lines of the group on the same day are greater than the capacity of the resources assigned to the group. Lines of the type Resource Group and lines with resources that belong to this group are counted. |
| Item conflict | Item, only inventory items | the available quantity of the item at the location of the line on the execution date, minus the demand of other work order lines with the same item on the same day, is less than the outstanding quantity – and there is no purchase order for the line yet. Non-inventory items never cause a conflict. |
| External service conflict | External Service | there is no purchase order for the line yet. Every external service that has not been ordered is therefore a conflict until you order it. |
You define the capacity of resources in Business Central on the resource (resource capacity). If a resource has no capacity for a day, any planning on that day causes a conflict. How to set up resource groups with units of measure for planning is described in Set up resource groups for work order planning.
When maintool calculates conflicts
maintool does not store conflicts but recalculates them each time the lines are displayed or changed:
- on the work order card, on the Lines FastTab, in the Conflicts column,
- in the Work Order List, in the Conflict column, and in the Work Order Conflicts FactBox.
The display is therefore always up to date. Because other work orders are also counted, a conflict can appear or disappear without you changing this work order – for example, when another work order plans the same person on the same day or when a purchase order is created.
In the Work Order List, a work order is also marked as a conflict if its Execution Date-Time field is empty.
View conflicts
In the planning lines
Open the work order. On the Lines FastTab, the Conflicts column is selected for every line with a conflict. You enter planning lines as described in Enter planning lines.
In the Work Order List with the Work Order Conflicts FactBox
- Open the Work Order List: in the work planning Role Center using the Work Orders action or one of the work order tiles, for example Overdue or Current. Alternatively, search for Work Order List.
- Select a work order. The Conflict column shows whether the work order has conflicts.
- The Work Order Conflicts FactBox shows only the lines of the selected work order that have a conflict, with Type, No., Description, outstanding Quantity and, for items and external services, Inventory and Qty. on Purch. Order.
The Work Order Conflicts FactBox and the solution proposals are only available in the Work Order List, not on the work order card. On the work order card, you only see conflicts in the Conflicts column of the lines.
Use solution proposals
- In the Work Order List, select the work order.
- In the Work Order Conflicts FactBox, select the line or lines you want to resolve.
- In the FactBox, choose the Show Solutionproposals action. The action is only visible if the work order has conflicts.
- If you have selected resources and items or external services at the same time, first choose which conflict to resolve: Resources or Items/External Services.
- Under Choose one of the following Solutions, select a proposal.
| Conflict for | Solution proposals |
| Resources | Portion workload to multiple days, Add additional resources, Portion Work Order to multiple shifts |
| Items and external services | Create Quote |
| Resource groups | none – maintool shows No Solution available. Adjust the quantity or date of the line yourself or plan specific resources. |
The proposals for resources are only available to users for whom the work planning Role Center is set up (Maintenance Workplanner Role Center Setup Card page). Other users receive the message No Solution available.
Portion workload to multiple days
maintool reduces the quantity of the selected resource line to the quantity already reported and distributes the open quantity over the following days, starting from the execution date of the line. For each day, maintool plans at most as much as the resource still has free on that day. New lines are created for these days with the respective date, 0:00. Afterwards, New Work Order Lines were created for the Work Order No. …! appears.
Everything planned for the resource counts as allocated here: work orders, projects and service orders. If the free capacity within one year is not sufficient, maintool stops with There is not enought free capacity for the Resource No. ….
Add additional resources
maintool opens the work order card. Add further lines with resources or resource groups there and reduce the quantity of the line with the conflict.
Portion Work Order to multiple shifts
- On the Shifts page, select one or more shifts. The shift of the work order itself is not offered.
- Confirm with OK and select the number series for the new work orders.
For each selected shift, maintool creates a follow-up work order with this shift. The reference object, assigned objects and dimensions are transferred, and the selected resource lines with the quantity 0. Each new work order opens. Enter the quantities there and reduce the quantity in the original work order. More about follow-up work orders in Create a follow-up work order.
Create Quote
For selected item and external service lines, maintool opens the Create Purchase Quote report, see Create a purchase quote or purchase order from a work order. The conflict only disappears once there is a purchase order for the line; a purchase quote alone is not enough.
Turn off conflict calculation
On the Work Order Management Setup page, on the Conflict Calculation FastTab, you specify which types of conflict maintool calculates: Calculate Resource Conflict, Calculate Item Conflict, Calculate External Service Conflict and Calculate Resource Group Conflict. All four are turned on by default. If a toggle is turned off, maintool no longer shows this type of conflict anywhere. Details in Set up work order management.