If further work arises from a work order, for example because a spare part must be ordered first or damage was discovered during maintenance, you create a follow-up work order. The follow-up work order is a separate work order that is linked to the original work order and takes over its technical objects and account assignment.
Prerequisites
- The original work order can have any status. You can also create follow-up work orders from closed and canceled work orders.
- A chain of follow-up work orders has a maximum of 8 levels (see below).
Create a follow-up work order
- Open the original work order. For a closed work order, open it from the Closed Work Orders list; for a canceled one, from Canceled Work Orders.
- Choose the Create Follow-Up Work Order action.
- If number series relationships are set up for the Work Order Nos., the Select No. Series window opens. Select the number series in the No. Series field and confirm with OK. If you do not select a number series, no follow-up work order is created.
Without number series relationships, no window appears and maintool uses the default number series. - maintool creates the follow-up work order and opens it. Add the description, planning lines and dates as for any other work order.
The follow-up work order starts in status Planning. How to continue is described in Enter planning lines and Schedule a work order and set it to execution.
What is transferred
| Transferred | Not transferred |
|
|
maintool fills in the remaining fields as for a new work order, for example the Work Order Posting Group from the Work Order Management Setup (General FastTab) and the work date as Execution Date-Time.
Link between the work orders
- In the follow-up work order, the Type of Origin field shows Work Order. The Origin Lines action shows the original work order. Use the Card action to open it.
- If the original work order is already Finished, Closed or Canceled when you create the follow-up work order, this origin line is reported finished right away. Such a follow-up work order cannot be canceled, see Cancel a work order.
- In the original work order, the Work Order History FactBox shows the number of direct follow-up work orders in the Follow-Up Work Orders field. Choose the number to open all work orders of the chain.
Levels
The original work order has level 1, its follow-up work order level 2, a follow-up of the follow-up work order level 3, and so on. More than 8 levels are not possible. In that case, the message The maximum number of levels is 8. appears and no follow-up work order is created. Create the follow-up work order from a work order higher up in the chain or create a new work order.
Delete the original work order
As long as follow-up work orders exist, the original work order cannot be deleted. The message You could not delete Work Order Header …, because follow-up orders are existing ! appears. Delete the follow-up work orders first. In general, work orders can only be deleted in status Planning; otherwise, cancel them, see Cancel a work order.