With the schedule board, you plan open work orders graphically: you drag a work order onto a person and a time, and maintool enters the person in charge and the dates directly in the work order. This shows you at a glance who is busy when and which work orders are not yet assigned to anyone.
Prerequisites
- The people who are to appear on the schedule board are set up as resources of the type Person. On the resource card, in the collana maintool section, the Use in Schedule Board field is turned on. For resources of the type Machine, the field cannot be turned on.
- You work in the Business Central web client.
- For the map view, a valid Bing Key is entered on the General FastTab of the Work Order Management Setup page. Without a key, the schedule board works, only the map is missing.
Open the schedule board
- In the work planning Role Center, in the Current area, choose the Schedule Board tile. The number on the tile shows how many work orders in the current period are not yet assigned to a person in charge.
- Alternatively, search for Schedule Board.
If no resource is set up for the schedule board, the message There are no resources for the Schedule Board. appears.
Layout of the schedule board
- Scheduler (top): There is one row per resource. Assigned work orders appear as bars with the work order number and description, colored in the color of their work order status. Using the view selection, you switch between Timeline (day), Timeline Week, Timeline Work Order Week, Work Order Week, Week, Month and Agenda. Today takes you to the current day.
- Work order list (bottom): All work orders from the status Planning up to, but not including, Finished, that is Planning, Execution, In Progress and Reported finished in mobile. The list shows Work Order No., Description, Work Order Status, Execution Date Time, Planned Completion Date Time, Person in Charge and the Location of Work column.
- Map (left, only with a Bing Key): The main locations of the work orders as markers in the status color. When you click a row in the work order list or the work order number on a bar, the map zooms to the location of work of that work order.
Rows highlighted in red in the work order list are work orders that are not yet assigned to a person in charge. As soon as you drag such a work order onto a resource, the highlighting disappears.
Legend and status colors
The Legend button at the bottom of the scheduler shows which color belongs to which work order status.
- Choose Legend.
- Click the color of a status and select a new color.
- Close the legend.
The scheduler and the map are displayed with the new colors.
maintool saves the color with the work order status. It therefore applies to all users. If a status does not have a color yet, the schedule board uses a default color.
Assign and move work orders
Assign a work order to a resource
- Select the work order in the work order list.
- Drag the row onto the row of the resource and the start time you want in the scheduler.
While you drag, a hint shows the current times and the description of the work order. - Release the mouse button.
maintool immediately saves in the work order:
- Person in Charge No. = the resource onto which you dragged the work order
- Execution Date-Time = the start time where you dropped the work order
- Planed Completion Date-Time = start time plus the previous duration of the work order. If the work order did not have a planned completion yet, maintool plans one hour.
As when you change the dates on the work order card, maintool also moves the execution date of the planning lines, see Schedule a work order and set it to execution.
Change an assignment
- Move: Drag the bar to another time or another resource.
- Change the duration: Drag the end of the bar. maintool adjusts the planned completion.
- Reassign from the list: If you drag an already assigned work order from the work order list onto the scheduler again, the new bar replaces the previous one.
- Remove the assignment: Click the cross in the bar. maintool clears the Person in Charge No.; the dates remain unchanged. The work order is highlighted in red in the list again.
Every change on the schedule board is saved in the work order immediately and without confirmation – even for work orders that already have the status Execution and whose person in charge can no longer be changed on the work order card. The schedule board does not check whether the resource is available at that time. You see availability conflicts in the work order, see Availability conflicts in the work order.
Edit locations of work on the schedule board
In the work order list, in the Location of Work column, choose Edit to open the Locations of Work window of the work order. There you can
- mark another location of work as the Main Location (only the main location appears on the map),
- remove a location of work with Delete,
- create a location of work using New Location of Work. Name, Address, Post Code, City and Country are mandatory. The post code and city must exist together in the Business Central post codes.
You edit all fields of the location of work, contact details and coordinates on the work order card, see Enter the location of work.