No new date: "New Date possible" is off

  • Updated

New Date possible is disabled on the time schedule (Interval FastTab) or on the object monitoring line (Date FastTab). In that case, no date proposal appears for this time schedule or line, and maintool does not create another work order from it. With the Create Work Order action on the time schedule or object monitoring line, for example, The Time Schedule Header … has at least one open Work Order Header. (Work Order Origin Line) appears.

When maintool allows a new date

  • As soon as a work order is created from a date, maintool disables New Date possible. Exception: with Set next Action at = Fixed Date, the field remains enabled and the dates follow a fixed rhythm.
  • maintool calculates the next date from the work order event in the Set next Action at field, plus the Time Interval:
    • Opening: time at which the work order was set to Execution (Opening Date-Time).
    • Execution: Execution Date-Time of the work order.
    • Finishing (default): time at which the work order or the origin line was finished.
    • Completing: time at which the work order was closed.
    With Opening, Finishing and Completing, New Date possible remains disabled until this event has occurred.
  • In addition, New Date possible remains disabled as long as an origin line for the time schedule or object monitoring line is still open in a work order. An origin line is open as long as it is neither finished nor marked as Not executed and its work order has not been canceled. This does not apply to Fixed Date.

You can see which work order belongs to the last date on the Date Handlings page (Handlings action). The Open Work Orders action on the time schedule or object monitoring line shows open work orders.

Causes and solutions

Cause Solution
The work order for the last date has not been finished yet. Finish the work order. maintool asks whether open origin lines are to be finished as well. If the work order combines several dates, you can finish individual origin lines beforehand via Origin Lines › Finish Work Order Text Line-Single (from status Execution). See Finish and close a work order.
Set next Action at is Completing, but the work order has only been finished. Close the work order. Finishing the origin line is not enough here.
The work will not be carried out, but the work order is still open. Cancel the work order. maintool then calculates the next date from the time of the cancellation. See Cancel a work order. If the work order combines several dates, mark only the affected origin line with Not execute Origin Line. maintool then removes the date from the date handling.
Several work orders from the time schedule or object monitoring line are open, for example from the time when Fixed Date was set. Complete all open work orders as described above. You find the list via Open Work Orders.
The next date would be after the Scheduling End Date-Time. maintool then sets the status Expired. Extend or clear the Scheduling End Date-Time if the activity is to continue. See Limit, block or phase out a time schedule.
For a new time schedule or object monitoring line, the Time Interval or the starting point (Time interval to Start or Starting Date-Time) is missing. Without Next Action at Date-Time, no new date is possible. Enter both values.

Notes and limitations

  • Initialize Time Schedule or Initialize Object Monitoring Line does not help here: both actions require New Date possible to be enabled already and otherwise stop with an error message. See Track dates and reinitialize a time schedule.
  • The status Blocked does not change New Date possible, but also prevents date proposals. See No date proposal appears.