Create a purchase quote or purchase order from a work order

  • Updated

If you need material or an external service from a supplier for a work order, create the purchase quote or purchase order directly from the planning lines of the work order. maintool transfers items, quantities and prices and links each purchase line to the planning line. This way, the receipt and the invoice are later posted to the correct work order automatically.

Prerequisites

  • The work order has a status from Planning to Finished.
  • The lines that you want to request or order have the type Item or External Service. Resources, resource groups and sales items cannot be purchased.

Prepare the planning lines

On the Lines FastTab of the work order, check these columns:

  • No., Quantity and Unit of Measure Code: A line with quantity 0 stops the process with the message Quantity in Line … is 0.
  • Buy-from Vendor No.: When you enter the line, maintool suggests the Vendor No. of the item. If lines have different vendors, each vendor gets a separate document. If a line has no vendor, you must specify a vendor in the dialog.
  • Direct Unit Cost: If the direct unit cost is 0, maintool stops with the message Direct Unit Cost in Line … is 0., unless creating documents is allowed in the Work Order Management Setup on the Purchase FastTab under Create Document if Direct Unit Cost = 0.

Create a purchase quote or purchase order

  1. Open the work order and go to the Lines FastTab.
  2. Select the lines that you want to request or order. To select several lines, use Select More.
  3. Choose Functions > Create Purchase Quote or Functions > Create Order.
  4. Fill in the dialog (see below) and choose OK.

The same actions are also available directly on the work order card (Create Purchase Quote, Create Purchase Order). From there, maintool always transfers all item and external service lines of the work order; the Create from marked lines field is not available then.

Fields in the dialog

The dialog has the name of the selected action: Create Purchase Quote or Create Purchase Order.

Field Meaning
Create new Document On: maintool creates a new document. Off: maintool adds the lines to an existing document.
Vendor No. New document: All lines go into one document for this vendor. Empty: maintool creates one document per Buy-from Vendor No. of the lines.
Existing document: limits the selection in Document No. to this vendor.
Document No. Existing document: Select the purchase quote or purchase order to which the lines are added (mandatory).
New document: optionally a manual number.
No. Series New document only: number series for the new document. If you leave Document No. and No. Series empty, Business Central assigns the number from the default number series for purchase quotes or purchase orders.
Copy prices from lines On: maintool takes the Direct Unit Cost from the planning lines. Off: Business Central determines the price as for a manually entered purchase line.
Create from marked lines On: only the selected lines. Off: all item and external service lines of the work order. Only visible if you start the action from the lines.
Responsibility Center Optional: responsibility center for a new document.

Result

maintool confirms with New Quotes are created. or New Orders are created. or, for an existing document, New lines for Quote … are created. or New lines for Order … are created.

  • The posting date, order date and requested receipt date of a new document correspond to the execution date of the work order. maintool takes the currency and dimensions from the work order.
  • Each purchase line contains Work Order No. and Line No. (Work Order), plus the description, quantity, unit of measure, variant, location and bin from the planning line.
  • If the vendor has Prices Including VAT, maintool increases the direct unit cost from the work order (net) by the VAT.
  • maintool transfers unplanned lines that were added after the change to Execution like planned lines, see Enter planning lines.

View the documents for the work order

In the Work Order History FactBox of the work order card, Purchase Quotes and Orders show how many documents belong to the work order. Choose the number to open the list and open the document with Card. In the lines of the document, you can see the link to the work order in Work Order No. and Line No. (Work Order).

As long as a purchase quote or purchase order contains lines for this work order, you cannot close or cancel the work order, see Finish and close a work order. Select only item and external service lines: If resource, resource group or sales item lines are selected, maintool stops.

Available from version 20260800.0: The action is called Create Purchase Quote (previously "Create Quote"). Unplanned lines are no longer skipped when creating a purchase quote. For vendors with Prices Including VAT, the direct unit cost is increased by the VAT.