Maintenance – Workplanner Role Center

  • Updated

The Maintenance - Workplanner Role Center gives you a quick overview of overdue, current and future work order requests, work orders, purchase orders and date proposals. The tiles are grouped into Overdue, Current and In Future/Planning. You control which records a tile counts in the setup of the Role Center.

This article describes the setup, how the periods and date proposals are calculated and, for each tile, what it counts.

Role Center setup

The setup applies per user. When a user opens the Role Center for the first time, maintool creates the user's setup with default values. This also creates a separate date proposal name RC_<User ID>. It is intended for the Role Center and takes time schedules and object monitoring lines into account.

You open the setup by searching for Workplanner Role Center Setups and selecting the user's line. The Maintenance Workplanner Role Center Setup Card page opens. In the Maintenance Role Center, you can also reach it via Setup > Role Center Setup > Maintenance WorkPlanner Role Center Setup Card.

FastTab Field Meaning Default value
General User ID User to whom the setup applies. signed-in user
General Date Proposal Name Date proposal name that maintool uses to calculate the date proposals for the Role Center. Only date proposal names with Used for Role Center turned on can be selected. The filters of the date proposal name apply, except for the filter on the responsible department (see next field). RC_<User ID>
General Responsible for Department Filter on the responsible department (Res. Department No.). Applies to work order requests, work orders and date proposals, not to purchase orders. For the date proposals, this value is used instead of the department filter in the date proposal name. Blank means: no filter. blank
General Prevoius Period How far the overdue period reaches back before the current period. Only negative date formulas are allowed, for example -7D. -7D
General Actual Period Basis for the current period: Day, Week or Month. Week
General Actual Period Additional Time Extends the current period into the future. Only positive date formulas are allowed, for example 7D. 7D
General Future Period How far the future period reaches beyond the end of the current period. Only positive date formulas are allowed. 31D
Cues Status Range Overdued Work order status values for the Overdue Work Orders tile, for example 100..269 for all work orders that have not been reported finished yet. 100..269
Cues Calculation Interval How often maintool recalculates the date proposals when the Role Center opens: Always, Hourly or Daily (see How the date proposals are calculated). Always

Available from version 20261000.0: the Calculation Interval field. In older versions, maintool recalculates the date proposals every time the Role Center opens.

How the periods are calculated

maintool calculates all periods when the Role Center opens, based on the work date. Each period starts at 00:00 and ends at 23:59.

  • Current period: Start and end result from the Actual Period. The end is extended by the Actual Period Additional Time.
    • Day: from the work date to the work date plus additional time.
    • Week: from Monday of the current week to Sunday plus additional time.
    • Month: from the last day of the previous month to the end of the month plus additional time. The last day of the previous month already belongs to the current period.
  • Overdue period: ends on the day before the start of the current period and starts the Prevoius Period before the start of the current period.
  • Future period: starts on the day after the end of the current period and ends the Future Period after the end of the current period.

Examples

All examples are based on the work date Tuesday, 01/21/2025.

Actual Period Overdue (Prevoius Period -1D) Overdue (Prevoius Period -7D) Current (no additional time) Current (additional time 7D) Future (additional time 7D, Future Period 7D)
Day 01/20/2025 01/14 – 01/20/2025 01/21/2025 01/21 – 01/28/2025 01/29 – 02/04/2025
Week 01/19/2025 01/13 – 01/19/2025 01/20 – 01/26/2025 01/20 – 02/02/2025 02/03 – 02/09/2025
Month 12/30/2024 12/24 – 12/30/2024 12/31/2024 – 01/31/2025 12/31/2024 – 02/07/2025 02/08 – 02/14/2025

With the default values (Week, Prevoius Period -7D, additional time 7D, Future Period 31D), this results in: overdue 01/13 – 01/19/2025, current 01/20 – 02/02/2025, future 02/03 – 03/05/2025.

If Future Period is blank, there is no valid future period. The Future planned Work Orders tile then counts no work orders. Therefore, always enter a Future Period.

How the date proposals are calculated

The tiles Overdue Date Proposals and Future Date Proposals count date proposals from time schedules and object monitoring lines. maintool calculates them with the Date Proposal Name from the setup, for all dates up to the end of the future period:

  • Dates that were due before the work date count as overdue.
  • Dates from the work date up to the end of the future period count as future.

With many time schedules and object monitorings, the calculation can take a few seconds. With the Calculation Interval in the setup, you specify how often maintool recalculates when the Role Center opens:

  • Always: The date proposals are recalculated every time the Role Center opens. The tiles are therefore always up to date.
  • Hourly or Daily: The date proposals are only recalculated if at least one hour or 24 hours have passed since the last calculation. The Role Center therefore opens faster, but the numbers of the two tiles can be outdated until the next calculation. The interval starts at the time you set it.

With the Update action in the Date Proposal List, you can trigger a recalculation at any time, regardless of the interval. The interval then starts again. After you have created work orders in the Date Proposal List, maintool also recalculates the date proposals.

Tiles

A click on a tile opens the list of the counted records. Where the table says Res. Department, the filter from the Responsible for Department field of the setup applies.

Tile Counts Date and period Further filters
Overdue
Overdue Work Order Requests registered work order requests Entry Date-Time in the overdue period Res. Department
Overdue Work Orders work orders with a work order status value from Status Range Overdued Execution Date-Time in the overdue period Res. Department
Overdue Date Proposals date proposals from time schedules and object monitoring lines due before the work date; the Prevoius Period has no effect here filters of the Date Proposal Name, Res. Department
Current
Current Work Order Requests registered work order requests Entry Date-Time in the current period Res. Department
Curr. Work Orders - Planning work orders with a work order status value from 100 to 199 (Planning), excluding standing orders Execution Date-Time in the current period Res. Department
Curr. Work Orders - Execution work orders with a work order status value from 200 to 299 (Execution up to before Finished), excluding standing orders Execution Date-Time in the current period Res. Department
Standing Work Orders standing orders with a work order status value from 100 to 299 no period Res. Department
Finished cur. Work Orders work orders with a work order status value from 300 to 399 (Finished) Execution Date-Time in the current period Res. Department
Schedule Board work orders with a work order status value from 100 to 299 that have no person in charge yet Execution Date-Time in the current period Res. Department
In Future/Planning
Planning assigned Purchase Orders purchase lines assigned to a work order expected receipt date from the work date to the end of the future period none; Res. Department has no effect here
Future Date Proposals date proposals from time schedules and object monitoring lines due from the work date to the end of the future period filters of the Date Proposal Name (for example shift), Res. Department
Future planned Work Orders work orders with the work order status value 100 (Planning) Execution Date-Time in the future period Res. Department

Examples for Planning assigned Purchase Orders (work date 01/21/2025, additional time 7D, Future Period 7D): Day 01/21 – 02/04/2025, Week 01/21 – 02/09/2025, Month 01/21 – 02/14/2025.

A click on the Schedule Board tile opens the schedule board, where you assign the orders to persons in charge. The schedule board is only available in the web client. In other clients, the message Please use Web Client for the Schedule Board! appears.

Actions

With the actions New Work Order Request and New Work Order, you create a new work order request or a new work order directly from the Role Center.