The Maintenance - Workplanner Role Center gives you a quick overview of overdue, current and future work order requests, work orders, purchase orders and date proposals. The tiles are grouped into Overdue, Current and In Future/Planning. You control which records a tile counts in the setup of the Role Center.
This article describes the setup, how the periods and date proposals are calculated and, for each tile, what it counts.
Role Center setup
The setup applies per user. When a user opens the Role Center for the first time, maintool creates the user's setup with default values. This also creates a separate date proposal name RC_<User ID>. It is intended for the Role Center and takes time schedules and object monitoring lines into account.
You open the setup by searching for Workplanner Role Center Setups and selecting the user's line. The Maintenance Workplanner Role Center Setup Card page opens. In the Maintenance Role Center, you can also reach it via Setup > Role Center Setup > Maintenance WorkPlanner Role Center Setup Card.
| FastTab | Field | Meaning | Default value |
| General | User ID | User to whom the setup applies. | signed-in user |
| General | Date Proposal Name | Date proposal name that maintool uses to calculate the date proposals for the Role Center. Only date proposal names with Used for Role Center turned on can be selected. The filters of the date proposal name apply, except for the filter on the responsible department (see next field). | RC_<User ID> |
| General | Responsible for Department | Filter on the responsible department (Res. Department No.). Applies to work order requests, work orders and date proposals, not to purchase orders. For the date proposals, this value is used instead of the department filter in the date proposal name. Blank means: no filter. | blank |
| General | Prevoius Period | How far the overdue period reaches back before the current period. Only negative date formulas are allowed, for example -7D. | -7D |
| General | Actual Period | Basis for the current period: Day, Week or Month. | Week |
| General | Actual Period Additional Time | Extends the current period into the future. Only positive date formulas are allowed, for example 7D. | 7D |
| General | Future Period | How far the future period reaches beyond the end of the current period. Only positive date formulas are allowed. | 31D |
| Cues | Status Range Overdued | Work order status values for the Overdue Work Orders tile, for example 100..269 for all work orders that have not been reported finished yet. | 100..269 |
| Cues | Calculation Interval | How often maintool recalculates the date proposals when the Role Center opens: Always, Hourly or Daily (see How the date proposals are calculated). | Always |
Available from version 20261000.0: the Calculation Interval field. In older versions, maintool recalculates the date proposals every time the Role Center opens.
How the periods are calculated
maintool calculates all periods when the Role Center opens, based on the work date. Each period starts at 00:00 and ends at 23:59.
-
Current period: Start and end result from the Actual Period. The end is extended by the Actual Period Additional Time.
- Day: from the work date to the work date plus additional time.
- Week: from Monday of the current week to Sunday plus additional time.
- Month: from the last day of the previous month to the end of the month plus additional time. The last day of the previous month already belongs to the current period.
- Overdue period: ends on the day before the start of the current period and starts the Prevoius Period before the start of the current period.
- Future period: starts on the day after the end of the current period and ends the Future Period after the end of the current period.
Examples
All examples are based on the work date Tuesday, 01/21/2025.
| Actual Period | Overdue (Prevoius Period -1D) | Overdue (Prevoius Period -7D) | Current (no additional time) | Current (additional time 7D) | Future (additional time 7D, Future Period 7D) |
| Day | 01/20/2025 | 01/14 – 01/20/2025 | 01/21/2025 | 01/21 – 01/28/2025 | 01/29 – 02/04/2025 |
| Week | 01/19/2025 | 01/13 – 01/19/2025 | 01/20 – 01/26/2025 | 01/20 – 02/02/2025 | 02/03 – 02/09/2025 |
| Month | 12/30/2024 | 12/24 – 12/30/2024 | 12/31/2024 – 01/31/2025 | 12/31/2024 – 02/07/2025 | 02/08 – 02/14/2025 |
With the default values (Week, Prevoius Period -7D, additional time 7D, Future Period 31D), this results in: overdue 01/13 – 01/19/2025, current 01/20 – 02/02/2025, future 02/03 – 03/05/2025.
If Future Period is blank, there is no valid future period. The Future planned Work Orders tile then counts no work orders. Therefore, always enter a Future Period.
How the date proposals are calculated
The tiles Overdue Date Proposals and Future Date Proposals count date proposals from time schedules and object monitoring lines. maintool calculates them with the Date Proposal Name from the setup, for all dates up to the end of the future period:
- Dates that were due before the work date count as overdue.
- Dates from the work date up to the end of the future period count as future.
With many time schedules and object monitorings, the calculation can take a few seconds. With the Calculation Interval in the setup, you specify how often maintool recalculates when the Role Center opens:
- Always: The date proposals are recalculated every time the Role Center opens. The tiles are therefore always up to date.
- Hourly or Daily: The date proposals are only recalculated if at least one hour or 24 hours have passed since the last calculation. The Role Center therefore opens faster, but the numbers of the two tiles can be outdated until the next calculation. The interval starts at the time you set it.
With the Update action in the Date Proposal List, you can trigger a recalculation at any time, regardless of the interval. The interval then starts again. After you have created work orders in the Date Proposal List, maintool also recalculates the date proposals.
Tiles
A click on a tile opens the list of the counted records. Where the table says Res. Department, the filter from the Responsible for Department field of the setup applies.
| Tile | Counts | Date and period | Further filters |
| Overdue | |||
| Overdue Work Order Requests | registered work order requests | Entry Date-Time in the overdue period | Res. Department |
| Overdue Work Orders | work orders with a work order status value from Status Range Overdued | Execution Date-Time in the overdue period | Res. Department |
| Overdue Date Proposals | date proposals from time schedules and object monitoring lines | due before the work date; the Prevoius Period has no effect here | filters of the Date Proposal Name, Res. Department |
| Current | |||
| Current Work Order Requests | registered work order requests | Entry Date-Time in the current period | Res. Department |
| Curr. Work Orders - Planning | work orders with a work order status value from 100 to 199 (Planning), excluding standing orders | Execution Date-Time in the current period | Res. Department |
| Curr. Work Orders - Execution | work orders with a work order status value from 200 to 299 (Execution up to before Finished), excluding standing orders | Execution Date-Time in the current period | Res. Department |
| Standing Work Orders | standing orders with a work order status value from 100 to 299 | no period | Res. Department |
| Finished cur. Work Orders | work orders with a work order status value from 300 to 399 (Finished) | Execution Date-Time in the current period | Res. Department |
| Schedule Board | work orders with a work order status value from 100 to 299 that have no person in charge yet | Execution Date-Time in the current period | Res. Department |
| In Future/Planning | |||
| Planning assigned Purchase Orders | purchase lines assigned to a work order | expected receipt date from the work date to the end of the future period | none; Res. Department has no effect here |
| Future Date Proposals | date proposals from time schedules and object monitoring lines | due from the work date to the end of the future period | filters of the Date Proposal Name (for example shift), Res. Department |
| Future planned Work Orders | work orders with the work order status value 100 (Planning) | Execution Date-Time in the future period | Res. Department |
Examples for Planning assigned Purchase Orders (work date 01/21/2025, additional time 7D, Future Period 7D): Day 01/21 – 02/04/2025, Week 01/21 – 02/09/2025, Month 01/21 – 02/14/2025.
A click on the Schedule Board tile opens the schedule board, where you assign the orders to persons in charge. The schedule board is only available in the web client. In other clients, the message Please use Web Client for the Schedule Board! appears.
Actions
With the actions New Work Order Request and New Work Order, you create a new work order request or a new work order directly from the Role Center.