Create a time schedule with object reference

  • Updated

For recurring activities on technical objects, for example the inspection of a pressure vessel or of all electrical devices in a hall, you create a time schedule of type Object Monitoring Template. It describes the activity once: lines, texts and defaults for the work order. You do not define in the time schedule when the activity is due, but for each object in an object monitoring line. This way, many objects use the same time schedule, each with its own interval.

Prerequisites

  • In the Work Order Management Setup (Numbering FastTab), a number series is entered in the Time Schedule Nos. field.
  • The technical objects (component addresses, mounting positions, technical components or vehicles) have been created.

Create a time schedule

  1. In the work planning Role Center, choose the Time Schedule action. Alternatively, open the Time Schedules list and choose New.
  2. On the General FastTab, fill in the Description, if required also Description 2 and Description 3, as well as Person in Charge No., Resp. Department No. and Work Order Category Code.
    maintool transfers the descriptions to every object monitoring line that uses this time schedule.
  3. In the Type field, select Object Monitoring Template.
    The fields on the Interval FastTab are now locked, and the Time Schedule Object Monitoring Lines FactBox and the Object Monitoring Lines action appear.
  4. On the Activity FastTab, enter the Type of Activity Code, Shift Code, Work Order Priority Code and, if required, the Work Plan No.
  5. On the Accounting FastTab, check the Work Order Posting Group and add budget or further job costing if required.
  6. On the Appointments FastTab, enter the Execution Day, Work Order Duration and standstill if required. These details apply to all objects.
  7. On the Lines FastTab, enter material, personnel and external services, and use the Texts action to add instructions, work notices or checklists.

How to enter lines, execution days and texts is described in Create a time schedule without object reference; it applies here in the same way. The meaning of all fields is described in Time schedule – fields and FastTabs.

Assign objects

For dates to be created, you assign the technical objects to the time schedule. For each object, an object monitoring line with its own Time Interval and Starting Date-Time is created. You can do this directly from the time schedule with the Object Monitoring Lines action or from the technical object with the Monitoring action. Both ways are described in Assign objects to a time schedule.

The Time Schedule Object Monitoring Lines FactBox shows which objects are already assigned to the time schedule.

Result

The time schedule is ready as a template. As soon as objects are assigned, maintool calculates the dates for each object. Due dates appear as date proposals. A work order created from them gets the object as Reference Object and Detail No., the lines, texts and comments of the time schedule, and the defaults from the Activity, Accounting and Appointments FastTabs. For a single work order, maintool takes the dimensions from the technical object. More on this in Create a work order from a date proposal.

Notes and limitations

  • If the time schedule already contains details on the Interval FastTab, maintool asks when you change to Object Monitoring Template: There are still informations existing on page intervall. Change Type anyway? With Yes, maintool clears the fields. Once a work order has been created from the time schedule, the change is no longer possible.
  • You can only change back to the type Time Schedule as long as no object monitoring line uses the time schedule. Otherwise, the message You can not modify Type, because there are existing object monitoring lines. appears.
  • If you block the time schedule (Status field), no more dates are created for any of the assigned objects, see Limit, block or phase out a time schedule.
  • If dates are to become due not by time but by a counter reading or consumption, link the time schedule to an object monitoring template, see Set up counter and consumption monitoring with an activity.