maintool logs every date of a time schedule and of every object monitoring line in the date handling. From this, maintool calculates the next date and decides whether a new work order can be created. This article explains how the dates are continued, where you can see the history, how to reinitialize a time schedule and when a time schedule can be deleted.
How the next date is created
- On creation, maintool creates a Start Record. The starting point is Time interval to Start (time schedule) or Starting Date-Time (object monitoring line). The first date is this point in time plus Time Interval.
- When a work order is created for the date, maintool creates a new entry with the Work Order No. New Date possible is then not enabled, except for Fixed Date.
- With every status change of the work order, maintool updates the entry. Depending on Set next Action at, maintool takes a point in time of the work order as the Activity Date-Time (see table).
- The next date (Next Action at Date-Time) is Activity Date-Time plus Time Interval. maintool enables New Date possible again when the selected event has occurred and no origin line from this time schedule or object monitoring line is still open. An origin line counts as completed if it has been finished or marked as not executed, or if its work order has been canceled.
| Set next Action at | Activity Date-Time | As long as the event is missing |
| Opening | Opening Date-Time (change to Execution) | maintool provisionally uses the Execution Date-Time; New Date possible is not enabled. |
| Execution | Execution Date-Time of the work order | – |
| Finishing | Manually finished at Date-Time of the origin line, otherwise Reported finish at Date-Time of the work order | maintool provisionally uses the Execution Date-Time; New Date possible is not enabled. |
| Completing | Reported complete at Date-Time of the work order | maintool provisionally uses the finishing or the Execution Date-Time; New Date possible is not enabled. |
| Fixed Date | previous date (Fixed Date-Time), regardless of the work order | New Date possible remains enabled. Open work orders do not prevent a further work order. |
This also applies to the running work order itself: with Opening and Execution, the setting only determines from when the calculation starts; a new date is nevertheless only possible once the origin line of the work order is completed. As long as a work order from the time schedule or object monitoring line is still open, no further work order can be created, except for Fixed Date. If you change the Execution Date-Time in the work order, maintool also recalculates. How to finish individual origin lines in advance or mark them as not executed is described in Finish and close a work order. maintool removes an origin line that is not executed from the date handling again; the time schedule is then back in the state it was in before the work order.
Canceled work orders
If you cancel a work order from a time schedule or an object monitoring line, maintool treats it like a completed work order in the date handling:
- The point in time of the cancellation is shown in the Canceled at Date-Time field and taken as the Activity Date-Time.
- The next date is the point in time of the cancellation plus Time Interval.
- New Date possible is enabled, provided that no other work order from the time schedule or object monitoring line is still open.
- Canceled work orders no longer prevent you from deleting the time schedule or object monitoring line.
How to cancel a work order is described in Cancel a work order.
Available from version 20261000.16: A canceled work order counts as completed in the date handling, and the Canceled at Date-Time field shows the point in time of the cancellation. Previously, New Date possible remained disabled after a cancellation. When updating to this version, maintool corrects such time schedules and object monitoring lines.
View dates and work orders
You can find the following actions on the Time Schedule page and in the Time Schedules list. For object monitoring lines, Handlings, Previews, Open Work Orders and Closed Work Orders are available on the Time Schedule Object Monitoring Lines, Object Monitoring Lines and Object Monitoring Line - Card pages.
| Action | What you see |
| Handlings | Date Handlings page: all previous dates with Start Record, Last Date, Work Order No., Work Order Status, Set next Action at, Activity Date-Time, Time Interval, Next Action at Date-Time, New Date possible and the points in time Opening Date-Time, Execution Date-Time, Reported finish at Date-Time, Reported complete at Date-Time and Canceled at Date-Time. For fixed dates also Generated by Fixed Date and Fixed Date-Time. |
| Previews | Time Schedule Previews page: the future dates calculated in advance, see Set up the date preview. |
| Open Work Orders, Closed Work Orders | Work orders that were created from the time schedule or object monitoring line. |
| Statistics | Time Schedule Statistics page (time schedule only): Time Schedule Flow Paths counts the dates with a work order after which a new date became possible. Complete Time Schedule Duration adds up, for these dates, the time from the opening of the work order to the execution, finishing or closing, depending on Set next Action at. The statistics only evaluate the dates of the time schedule itself, not those of its object monitoring lines. |
Initialize a time schedule
You can only change the starting point of the calculation via Time interval to Start or Starting Date-Time as long as no work order has been created. If the cycle is to start from a new point in time after that, for example after a longer shutdown, you reinitialize the time schedule.
- Open the time schedule (type Time Schedule) and check that New Date possible is enabled.
- Choose the Initialize Time Schedule action.
- In the dialog, enter the new Time interval to Start and confirm.
- Check Next Action at Date-Time.
maintool deletes the dates calculated in advance, creates a new start record and calculates the next date as the new Time interval to Start plus Time Interval. The previous entries in the Date Handlings are kept.
For object monitoring lines, choose the Initialize Object Monitoring Line action. For the type of monitoring Date, maintool asks for the new Starting Date-Time; for the other types of monitoring, the calculation restarts with the Initial Value.
- If New Date possible is not enabled, maintool stops with an error message on this field. First finish or cancel the open work order.
- If no work order has been created from the time schedule yet, the action does not change anything. In that case, simply change Time interval to Start.
Delete a time schedule or object monitoring line
When you delete a time schedule, maintool also deletes its lines, texts, comments, the date handling and the related date proposals. When you delete an object monitoring line, maintool removes its date handling, date proposals and dependencies. Work orders that have already been created are kept. Deleting is not possible in these cases:
| Message | Cause and solution |
| Time Schedule … could not be deleted, because there are still some open Work Orders! | There is a work order from the time schedule whose origin line has not been finished yet. Finish or cancel it. |
| Time Schedule … could not be deleted, because there are Object Monitoring Line existing! | Object monitoring lines use the time schedule. Delete them first, or set the status of the time schedule to Blocked. |
| Object Monitoring Line … could not be deleted, because there are still some open Work Orders! | There is a work order from the line whose origin line has not been finished yet. Finish or cancel it. |
| Object Monitoring Line … could not deleted, because there are Performance Characteristics Ledger Entry existing. | Performance characteristics have been posted for the line. Set the status to Deleted or Blocked instead. |
Work orders that have been canceled or whose origin lines are marked as not executed do not prevent deletion.