Create a time schedule without object reference

  • Updated

You create a time schedule without object reference for recurring activities that are not tied to a technical object, for example safety briefings or the regular check of driving licenses. The interval is defined in the time schedule itself. maintool calculates the dates from it and creates a work order without reference object from each date.

Prerequisites

  • In the Work Order Management Setup (Numbering FastTab), a number series is entered in the Time Schedule Nos. field. Without this number series, you cannot create a time schedule.

Create a time schedule

  1. In the work planning Role Center, choose the Time Schedule action. Alternatively, open the Time Schedules list and choose New.
    maintool assigns the number from the number series as soon as you move to a field other than No.
  2. On the General FastTab, fill in the Description, if required also Description 2 and Description 3, as well as Person in Charge No. and Resp. Department No. Leave the value Time Schedule in the Type field.
  3. Select a Work Order Category Code if required. If the category has default values, maintool asks whether you want to transfer them (type of activity, work order posting group, further job costing and dimensions).
  4. On the Activity FastTab, enter the Type of Activity Code, Shift Code and Work Order Priority Code. If you select a Work Plan No., maintool immediately starts Transfer Work Plan Data and transfers the details, lines and texts of the work plan.
  5. On the Interval FastTab, define when the activity is due: Set next Action at, Time Interval (for example 3M for three months) and Time interval to Start (see below).
  6. Check the Next Action at Date-Time field on the same FastTab. It shows the first date.
  7. On the Accounting FastTab, check the Work Order Posting Group (default from the Work Order Management Setup) and add dimensions, budget or further job costing if required.
  8. On the Appointments FastTab, enter the Execution Day, Work Order Duration and, if the equipment is shut down during the work, Standstill with Standstill Day and Standstill Duration if required.
  9. On the Lines FastTab, enter the material, personnel and external services that are planned for each execution (see below).
  10. Use the Texts action to add instructions, work notices or checklists, and Comments for further information. maintool transfers both to every work order.

The meaning of each field is described in Time schedule – fields and FastTabs.

Define the first date

maintool calculates the first date from Time interval to Start and Time Interval: Next Action at Date-Time = Time interval to Start + Time Interval. The time of day from Time interval to Start is kept.

  • If the activity has already taken place, enter that point in time as Time interval to Start.
  • If the first date is to fall on a specific day, count back by the time interval. Example: first date on 03/01/2027 with a time interval of 1Y – enter 03/01/2026 as Time interval to Start.
  • The Time Interval must point to the future, for example 1W, 3M or 1Y.

If you change Time interval to Start, maintool only recalculates as long as no work order has been created from the time schedule. After that, you restart the cycle with Initialize Time Schedule, see Track dates and reinitialize a time schedule.

Set next Action at

With Set next Action at, you define the point in time from which maintool calculates the next date after a work order. The next date is then one Time Interval after this point in time.

Value The next date is calculated from
Opening the point in time at which the work order is set to Execution (Opening Date-Time)
Execution the Execution Date-Time of the work order
Finishing (default) the point in time at which the work order is finished or its origin line is finished manually
Completing the point in time at which the work order is closed
Fixed Date the previous date, regardless of the work order. The dates stay in a fixed cycle, for example for legally required inspections.

How maintool continues the dates step by step and what applies to canceled work orders is described in Track dates and reinitialize a time schedule. If you change from Fixed Date to another value, maintool asks Do you really want, that the Time Schedule … does not create Fixed Dates anymore?

Enter time schedule lines

maintool transfers the lines of the time schedule to every work order that is created from the time schedule. You define the kind of line in the Type column:

Type Selection in No.
(blank) Standard text, or free text in Description
Item Inventory and non-inventory items that have no maintool Item Type
External Service Items of type Service, see Set up external service items
Resource Resources
Resource Group Resource groups

After the selection in No., maintool fills in the description, unit of measure and prices. Enter the Quantity. You can show further columns such as Location Code, Variant Code, Work Type Code, Buy-from Vendor No. or Execution Day by personalizing the page. How to update the prices later is described in Update prices in time schedules.

Execution Day

If the work takes several days, use the Execution Day to distribute the demand over the days:

  • On the Appointments FastTab: The work order gets the date (Next Action at Date-Time) plus the specified number of days as its Execution Date-Time.
  • In a line: Execution day 1 is the execution day of the work order, execution day 2 the day after, and so on. Without a value, the line gets the execution date of the work order.

If you change the Execution Day on the Appointments FastTab, maintool shifts the execution day of all lines by the same number of days.

Explode BOM

  1. Enter a line of type Item with a BOM item and the quantity.
  2. On the Lines FastTab, choose Functions > Explode BOM.
  3. Select where the dimensions should come from: Copy dimensions from BOM or Retrieve dimensions from components.

maintool replaces the BOM line with the components of the BOM, multiplied by the quantity. Components of type resource become lines of type Resource. If the item is not a BOM, the message Item … is not a bill of materials. appears.

Texts and comments

The Texts action opens the Time Schedule Texts page. Select Instruction or Work Notice in the Type field and the instruction or work notice in the Code field; maintool inserts its lines. How to add a checklist in this way is described in Add a checklist to a time schedule or work order.

Result

The time schedule has been created. On the Interval FastTab, Next Action at Date-Time, Calendar Week and Calendar Year show the next date, and New Date possible shows whether a work order can be created for it. When the date becomes due, it appears as a date proposal. You create the work order from it, see Create a work order from a date proposal. You can also create it directly from the time schedule, see Create a work order directly from a time schedule or object monitoring line.

Notes and limitations

  • Instead of entering everything again, you can use the Copy Document action to transfer the header, lines and texts from a work order, a work order feedback, a closed work order, a posted work order feedback or another time schedule.
  • The line type Sales Item, which work orders have from version 20261000.16, is not available in time schedule lines.
  • If you change the Sales to Customer No. on the Accounting FastTab, maintool asks whether the existing time schedule lines should be deleted and recreated with the new information. If you answer no, the message You must delete the existing time schedule lines before you can change … appears and the field remains unchanged.
  • A time schedule cannot be renamed.
  • If you change the Type to Object Monitoring Template, maintool clears the fields on the Interval FastTab after a confirmation. Once a work order has been created from the time schedule, the change is no longer possible (You could not modify Type from …, because there are still existing some other activities.).