Create a work order directly from a time schedule or object monitoring line

  • Updated

Usually, you create work orders for recurring activities from the date proposals of work planning, see Create a work order from a date proposal. However, you can also create the work order for the next date directly in the time schedule or in the object monitoring line, for example if you want to bring a maintenance forward. maintool transfers the same details as when creating it from the date proposal.

Prerequisites

  • In the Work Order Management Setup (Numbering FastTab), a number series is entered in the Work Order Nos. field.
  • The time schedule has a blank Status. For object monitoring lines, this applies to the line and to the time schedule it uses.
  • No work order from the time schedule or object monitoring line is still open. Exception: Set next Action at is set to Fixed Date.

Create a work order from a time schedule

This way applies to time schedules of type Time Schedule, that is, without object reference.

  1. Open the time schedule or select it in the Time Schedules list.
  2. Choose the Create Work Order action.
  3. Select the number series for the work order if required and confirm.
  4. Confirm the question Do you want to create a Work Order Header from this Time Schedule Header? with Yes.
    maintool reports Work Order Header … was created.

Create a work order from an object monitoring line

For one object

  1. Open the object monitoring line, for example via the Monitoring action on the technical object and then Card.
  2. Choose the Create Work Order action. In the Time Schedule Object Monitoring Lines list, it is called Create Work Order > Object Monitoring Line-Single.
  3. Select the number series if required and confirm.
  4. Confirm the question Do you want to create a Work Order Header from this Object Monitoring Line? with Yes.

For several objects at once

  1. Open the time schedule (type Object Monitoring Template) and choose the Object Monitoring Lines action.
  2. Select the lines of the objects. All selected lines must have the same Type, for example only technical components.
  3. Choose Create Work Order > Object Monitoring Line-Multiple and confirm the question Do you want to create one Work Order / multiple Work Orders from the Object Monitoring Line-Multiple?
  4. Select how the lines are combined:
    • One Work Order: The first selected line creates the work order; maintool adds the others as origin lines with their objects and lines.
    • Multiple Work Orders: A separate work order is created for each selected line.
  5. Select the number series if required and confirm.
    maintool reports the number of the work order or the number of work orders created.

Result

The work order has the status Planning. The Type of Origin in the work order is Time Schedule or Object Monitoring Line. The Execution Date-Time is the next date (Next Action at Date-Time), shifted by the Execution Day of the time schedule if applicable. maintool transfers the lines, texts, comments and defaults of the time schedule in the same way as when creating from the date proposal. What is transferred in detail is described in Create a work order from a date proposal.

  • From a time schedule without object reference, the work order has no Reference Object. The dimensions come from the time schedule.
  • From an object monitoring line, the object is entered as Reference Object and Detail No. The dimensions come from the technical object.

In the date handling, the date now shows the number of the work order. maintool calculates the next date as soon as the event selected under Set next Action at occurs, see Track dates and reinitialize a time schedule. Then you plan the work order as usual, see Schedule a work order and set it to execution.

If no work order is created

Message Cause and solution
The … has at least one open Work Order Header. (Work Order Origin Line) The work order for the previous date is still open. Finish or cancel it, see Track dates and reinitialize a time schedule.
Error message on the Status field The time schedule or object monitoring line is Blocked, Expired or Deleted, see Limit, block or phase out a time schedule.
Error message on the Type field (time schedule) The time schedule has the type Object Monitoring Template. Create the work order from the object monitoring line of the object.
Error message on the Blocked field The technical object is blocked.
Error message on the Time Interval, Interval or Initial Value field The interval is missing in the object monitoring line (for Attrition / Consumption also the Initial Value).
Error message on the Type of Monitoring field For object monitoring lines with the type of monitoring Threshold / Range, no work order can be created this way.
The work order cannot be created because … is blocked. Object monitoring line: an item or resource from the time schedule lines is blocked. Remove the block or change the time schedule line.
You can only process object Monitoring lines with the same Type! You have selected lines of different kinds of objects. Create the work orders per kind of object.

Notes and limitations

  • You can extend an existing work order from the date proposal or in the work order with Insert Origin Line, see Finish and close a work order.
  • With Fixed Date, maintool also creates the work order if a work order for the previous date is still open.